NEXT STEPS
·
GEF5 commencement
July 2010
·
GE
F OFP endorsements of PIF
May June/July 2010
·
GE
F OFP endorsement of co-financing
Submitted with the Pro Doc
·
Endorsed PIF submission to UNDP (who
June/July 2010
submit to GEF Sec on monthly basis)
·
PIF submission to GEF Sec
End of summer (September 2010) for the
November 2010 GEF Council
meeting
·
GEF CEO clears PIF to go to Council work
Allow for 4 weeks before GEF Council
programme
meeting for review by all GEF
Agencies, STAP review (PIF & STAP
review comments posted in the web
·
GEF Council Meeting
November 2010
·
Submission of Project Document
December 2009/Jan 2010
(GEF Sec review within 10 working days of
receiving Pro Doc, then circulated to
GEF Council - 4 weeks to comment)
·
GEF CEO endorsement
?
·
First GEF5 work program
Early 2011
·
Phase I conclusion ( no-cost extension)
End March 2011
·
Phase II commencement
April 2011
PROPOSED NEXT STEPS
· Informal comments on National Reports provided by Countries
to Mission consultants by 3 September
· National Reports final drafts returned to countries for formal
clearance by 30 September
· First draft of Project Document to Countries for informal
comment by 30 September with request for Letters of
Endorsement by 15 November
· Draft submitted to GEF for technical review at the same time
· Comments on draft Project Document provided by Countries
by October 15
· Final draft of Project Document to countries incorporating
country comments and GEF technical comments Countries by
October 31
· Project Document ready for submission to GEF Council by end
November
Document Outline